GLS is one of the leading providers of logistics and parcel services in Europe and has long been expanding its fleet with low-emission and electric vehicles. As part of the modernization of its central depot in Jihlava, building a robust and efficiently managed charging infrastructure became the key step – one that supports both daily operations and the future development of e-mobility.

To deliver the project, GLS chose MyBox, which supplied and installed the complete charging infrastructure including intelligent power management.

Project brief

The goal of the project was to:

  • build a charging infrastructure with sufficient capacity for the operational fleet

  • ensure efficient power management across the entire site

  • minimize the impact on the existing energy infrastructure

  • create a solution ready for further expansion

  • maintain a unified visual style matching the GLS brand

A row of MyBox Profi AC charging stations with electric vans at the GLS central depot in Jihlava

The implemented solution

Installation of MyBox Profi AC charging stations

A total of 20 MyBox Profi AC charging stations were installed at the central depot. The stations are arranged in two separate rows according to the operational needs of the site:

  • 12 stations in a row primarily for charging delivery vans (the logistics-area car park)

  • 8 stations in a row by the administrative building

This makes it possible to divide the charging infrastructure efficiently by type of operation and ensures the smooth daily running of the depot. The stations are finished in white with the GLS logo printed on them, so they blend naturally into the visual identity of the site while also giving the depot a polished, professional look.

An electric GLS delivery van charging at a MyBox Profi AC station at the Jihlava depot

DC fast charging

The solution also includes a 300 kW Alpitronic DC fast charger, which enables rapid charging of selected vehicles and complements the AC infrastructure for maximum operational flexibility. The infrastructure is also designed with further expansion in mind – additional AC and DC charging points are planned in the future as the fleet’s needs grow.

Key elements of the solution

  • 20× MyBox Profi AC charging station

  • layout across two operational zones (logistics / administration)

  • individual station branding (GLS design)

  • Alpitronic DC fast charger (300 kW)

  • combination of AC and DC charging for maximum flexibility

  • dynamic load management including quarter-hour peak control

  • a robust solution suited to logistics operations

  • readiness for further expansion of the infrastructure

MyBox Profi charging stations with GLS branding by the depot administrative building in Jihlava

Dynamic load management (DLM)

The entire charging infrastructure is managed by a dynamic load management (DLM) system that ensures the optimal distribution of available capacity across the site. The system controls all 20 MyBox Profi AC charging stations and the Alpitronic 300 kW DC station in real time.

Management also includes quarter-hour power-peak control, which prevents the reserved power from being exceeded and avoids unnecessary penalties from the distributor. This allows the available power to be used efficiently without the risk of overloading the grid. At the same time, the solution minimizes the need to intervene in the existing energy infrastructure and enables stable operation even under heavy load.

Project benefits

  • Efficient fleet operation – sufficient charging capacity for daily logistics operations without limitations.

  • Optimized energy performance – smart management including monitoring of quarter-hour maxima ensures maximum use of the available energy.

  • Charging flexibility – the combination of AC and DC makes it possible to adapt charging to different vehicle types and operating scenarios.

  • Scalability – the infrastructure is ready for further expansion with both AC and DC stations.

  • Unified design – the station branding supports the visual identity and professional appearance of the depot.

  • Stable, trouble-free operation – the solution is fully functional and stable, with no need for additional interventions.

Conclusion

The deployment of charging infrastructure at the GLS central depot in Jihlava represents a functional and scalable solution that meets the demands of modern logistics. The combination of AC and DC charging, intelligent power management including quarter-hour peak control, and readiness for further development create a stable foundation for the continuing electrification of the fleet.

The project confirms that well-designed infrastructure enables long-term, reliable operation without the need for additional interventions.

Considering a similar solution?

Planning to electrify your own fleet or set up charging for businesses? Take a look at the MyBox Profi AC charging stations and DC fast charging, or get inspired by our guide on how to choose an EV charger for your company. And don’t forget the current EV charging subsidies.